LEA leader: the developer of the first offshore wind farm “Ignitis Group” is struggling with project deadlines

LEA leader: the developer of the first offshore wind farm "Ignitis Group" is struggling with project deadlines

At that time, according to Agnė Bagočiutė, the “Ignitis Group” still states in its reports that it will fulfill its obligations on time, although it also acknowledges that the park will start producing electricity at least two years later – at the end of 2032.

Read more Research: Lithuania’s budget lost 109 million euros in revenue last year due to illegal tobacco

A. Bagočiutė claims to doubt that a construction permit will be obtained by February 12, 2027, and that electricity production will begin on February 12, 2030, as planned in the group’s initial commitment plan and the Renewable Energy Sources Act.